City Manager's Report For Feb. 4, 2020
Feb05

City Manager's Report For Feb. 4, 2020

Below is the City Manager’s Report presented By Marc Maxwell to Sulphur Springs City Council on February 04, 2020 WASTEWATER TREATMENT PLANT This project is completed. We will be paying the final bills this month. Budget for the project was $18,800,000. We expect total expenditures on the project to come in at $18,400,000. This project has finished on-time and under-budget. GRAYS’ BUILDING We have a set of plans for the Grays’...

Read More
City Manager's Report for December 2019
Dec05

City Manager's Report for December 2019

Below is the City Manager’s Report reported by Marc Maxwell Dec. 3, to Sulphur Springs City Council by Wastewater Treatment Plant The construction on all of the functional elements at the wastewater treatment plant is complete. All that remains is construction of the road. The plant is completely operational. Bellview Street The Bellview project has begun. Installation of sewer mains is ongoing. Connally Street The contractor on...

Read More
Sulphur Springs City Manager’s Report For Oct. 1, 2019
Oct02

Sulphur Springs City Manager’s Report For Oct. 1, 2019

Presented to the City Council by City Manager Marc Maxwell on Oct. 1, 2019 SUNSET STREET – This project is nearing completion. The Capital Construction Division is on the last segment of this street. You can see them setting forms for curb & gutter in the photo to the right. I expect them to finish in 3 weeks, as we will still need to tie-in some driveways. Work progresses on Sunset Street CONNALLY STREET – The contractor, 5W...

Read More
Sulphur Springs City Manager’s Report For Sept. 3, 2019
Sep04

Sulphur Springs City Manager’s Report For Sept. 3, 2019

Presented by Sulphur Springs City Manager Marc Maxwell during the Sept. 3, 2019 City Council meeting. Progress on street construction work SUNSET STREET – The Capital Construction Division is back at work on Sunset Street. We have changed the profile of the lay-down curbs to a gentler transition. This is a grant funded project through the Community Development Block Grant program. CONNALLY STREET – The contractor, 5W Contracting, has...

Read More
City Manager’s Report For Aug. 6, 2019
Aug07

City Manager’s Report For Aug. 6, 2019

PACIFIC PARK DRAINAGE PROJECT This project is progressing well. This project is finished. The barricades will remain in place until Friday so that the concrete will cure a bit more before we subject it to traffic. Allowing traffic on the concrete before it has had sufficient time to cure would lead to cracking and premature failure. The estimated final cost of the project is $43,000, well under the $85,000 budget. SUNSET STREET This...

Read More
City Manager’s Report Presented In July 2019 Council Meeting
Jul03

City Manager’s Report Presented In July 2019 Council Meeting

By Marc Maxwell, Sulphur Springs city manager PACIFIC PARK DRAINAGE PROJECT On Sept. 4, 2018, the City Council approved an expenditure of $85,000 to solve a drainage issue at Carter Street and Martin Luther King Jr. Drive. Since that time engineering has designed an alternative that is simpler and less expensive. It will be easier to maintain also. We have retained 5W Construction to perform the work. They plan to start next week....

Read More
City Manager’s Report Presented in May Council Meeting
May08

City Manager’s Report Presented in May Council Meeting

City Manager Marc Maxwell’s Report presented in the May City Council meeting included: CROSSTOWN TRAIL – The Capital Construction Division constructed a retaining wall at Coleman Park. Otherwise, the project is on hold until Connally is done or nearly done. Retaining wall constructed at Coleman Park, part of the Crosstown Trail project SPRING CLEANUP – The annual spring cleanup was a successful event. In total, Sanitation...

Read More
City Manager’s Report Presented in February Council Meeting
Feb06

City Manager’s Report Presented in February Council Meeting

City Manager Marc Maxwell’s Report presented in the February City Council meeting included: CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds and Peavine Pinion Pond. In January the Capital Construction Division poured more concrete, installed bike racks and trash cans, laid sod to prevent erosion, installed a water fountain and planted trees. SUNSET STREET – Work should begin on this...

Read More
Sulphur Springs City Manager’s Report January 8, 2019
Jan09

Sulphur Springs City Manager’s Report January 8, 2019

CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds. The Capital Construction division installed 200 linear feet of pathway and a retaining wall on the Civic Center grounds. SUNSET STREET – We have been waiting for bids for the rock. They came in today. Now our grant writer will review the bids for compliance with the grant requirements. Once we approve the bids we will get started on the...

Read More
City Manager’s Report June 5, 2018
Jun06

City Manager’s Report June 5, 2018

City Manager Marc Maxwell highlighted the work of city crews and improvements being made in the city during his report to the Sulphur Springs City Council Tuesday night in their June session. Activities included in his written report: SUNSET STREET – We have designed the Sunset Street improvements. The project will include new water mains, new sewer mains and a new concrete street from Connally to Houston.  The $275,000 CDBG grant is...

Read More