Tennis Complex on Schedule

roundtreeConsultant Don Roundtree gave the Sulphur Springs School Board a construction update and timeline on the High School Tennis Complex Monday night. Dirt work is expected to be finished in two to two and a half weeks. Concrete is scheduled to be poured for the building on August 1. The building should arrive on August 7. Roundtree said something vertical should be seen by mid-August. Completion date is projected as December 12.