Alliance Bank in Sulphur Springs
Bid For Concrete, Purchase Of Restroom Approved For Pacific Park
Jan06

Bid For Concrete, Purchase Of Restroom Approved For Pacific Park

The Pacific Park renovation progressed this week with Sulphur Springs City Council’s approval of a bid for concrete and purchase of a ready-to connect public restroom through an online purchasing cooperative. A $750,000 grant from the Land and Conservation Fund, administered through TPWD Recreation Grants Branch, will go toward renovations at Pacific Park. The city received only two very close bids from businesses interested in...

Read More
Sulphur Springs City Manager’s Report – Jan. 4, 2022
Jan05

Sulphur Springs City Manager’s Report – Jan. 4, 2022

Sulphur Springs City Manager Marc Maxwell presented the following report to the City Council during the regular monthly council meeting on Jan. 4, 2022. COVID-19 Response The Omicron variant of the COVID virus seems to be spreading like wildfire across the nation. Unfortunately, I cannot give you any accurate numbers regarding the number of local cases. The State of Texas is having difficulty updating the numbers. This has been a...

Read More
Park And Senior Center, Potential Economic Development Projects On Jan. 4 Agenda
Dec31

Park And Senior Center, Potential Economic Development Projects On Jan. 4 Agenda

Pacific Park and senior center projects as well as potential economic development projects are among the topics on the Sulphur Springs City Council Jan. 4 agenda. The City Council will first meet at 6:30 p.m. in executive session to consult with an attorney, discuss real property matters, specifically potential acquisition of property for storm drainage purposes, and to consider two economic development projects: one for D6 Inc. and...

Read More
Construction of Fitness Court Enters Next Phase
Dec28

Construction of Fitness Court Enters Next Phase

Construction of a fitness court in Pacific Park enters the second phase this week with additional ground work. Crews were out working Tuesday morning, cementing a blue layer of the project to the concrete foundation. The project should really start taking off, now that the foundation has had the requisite month to set. The second phase of construction on the outdoor fitness court was in progress Tuesday, Dec. 28, 2021, at Pacific...

Read More
Fitness Court Slab Latest Step In Pacific Park Improvements
Nov29

Fitness Court Slab Latest Step In Pacific Park Improvements

The latest step in the Pacific Park improvements is the setting of the fitness court slab. The slab was in place Monday morning, Nov. 29, 2021. It is required to set for 28 days before any additional work is possible, according to Sulphur Springs City Manager Marc Maxwell. With the new Grays Community Building complete and open to the public, the fitness court slab is the latest step in the Pacific Park improvement project. Assistant...

Read More
Sulphur Springs Officials Discuss City Tax Rate, Budget During Workshops
Aug13

Sulphur Springs Officials Discuss City Tax Rate, Budget During Workshops

Reduction In Tax Rate, Small Increase In Utility Fees Proposed Sulphur Springs officials have been hard at work this summer shaping and tightening up a budget for the 2021-2022 fiscal year. After two special meetings with Sulphur Springs City Council, officials anticipated proposing a city tax rate that will be not quite 2 cents lower, while recommending a small increase to city utility fees to keep up with inflation and apply toward...

Read More
City Awarded Grant to Help Construct Outdoor Fitness Court At Pacific Park
Jul08

City Awarded Grant to Help Construct Outdoor Fitness Court At Pacific Park

Stock Donated To Help Fund Senior Citizens Center Project Sulphur Springs officials this week reported both good and bad news regarding the planned senior citizens center project, and good news regarding the Pacific Park project as well. While the bid for the pre-engineered metal frame for the new Senior Citizens building was much high than city officials had anticipated, the city also received a stock donation to help the project and...

Read More
Results Of Survey, Steps In Pacific Park Improvement Plan Discussed
Mar30

Results Of Survey, Steps In Pacific Park Improvement Plan Discussed

With work on the Grays Building progressing rapidly, focus is turning more toward the park grounds. The results of the community survey conducted earlier this month and next steps in the Pacific Park improvement plan were outlined during a special Zoom meeting Monday night. Survey Results William Spencer, the civil engineer and partner MHS Planning & Design LLC, who came up with the design concept to enhance park facilities based...

Read More
Work On Grays Building Continues At Fast Pace
Mar29

Work On Grays Building Continues At Fast Pace

Zoom Meeting Scheduled This Evening To Discuss Pacific Park Survey Results, Next Steps In Park Improvement Project Courtesy Photo Progress on the Grays Building in Pacific Park continues at a smart pace. Today, glazers install glass while masons erect brick veneers on the east end of the building. Inside the building workers tape and bed the sheetrock, according to Sulphur Springs City Manager Marc Maxwell. A little over a week ago, a...

Read More
Work On Grays Building In Pacific Park Progressing With Roof Work
Mar18

Work On Grays Building In Pacific Park Progressing With Roof Work

Deadline For Community Members To Complete Online Pacific Park Improvements Survey Is March 19 Work on the Grays Building in Pacific Park is progressing with the roof being installed Wednesday. Crews were on scene using equipment to lift large metal panels to the top of the building to be placed and secured atop the metal frame. Over the last month, framing and plumbing top-out were finished. Electrical rough-in was nearly complete,...

Read More